The number of days in which A and B together can finish a piece of work is 12 days less than the time taken by A alone and 27 days less than the time taken by B alone to finish the work. If A and B completed the work in 15 days with the help of C and got a total compensation of Rs 3000 for the work, then what is the share of C?