It was calculated that 75 men could complete a piece of work in 20 days. When work was scheduled to commence,…

Q 122

It was calculated that 75 men could complete a piece of work in 20 days. When work was scheduled to commence, it was found necessary to send 25 men to another project. How long it will take to complete the work?

Show answerHide answer

Answer: Option C. 30

Keep practising