Atul takes 8 hours to do a job. Bhumi takes 10 hours to do the same job. How long should it take both Atul and…

Q 119

Atul takes 8 hours to do a job.  Bhumi takes 10 hours to do the same job. How long should it take both Atul and Bhumi, working together but independently, to do the same job?

Show answerHide answer

Answer: Option B. <span class="math-tex">4494\frac{4}{9}</span>