  1. Q 111

    J can dig a well in 16 days. P can dig a well in 24 days. J, P, H dig in 8 days.  H alone can dig the well in how many days?

  2. Q 112

    2 children and 3 men can do a work in 12 days while 3 children and 2 men can do the same work in 10 days. How many days it will take to complete the same work if 1 child and 1 man work together?

    Show answerHide answer

    Answer: Option C. <p><span class="math-tex">27311days27\frac{3}{{11}}days</span></p>

    Open question
  3. Q 113

    15 men take 21 days of 8 hrs. each to do a piece of work. How many days of 6 hrs. each would it take for 21 women if 3 women do as much work as 2 men?

  4. Q 114

    A tank is filled with water. In first hour 10 liters, second hours 20 liters, and third hour 40 liters and so on. If time taken to fill (1/4)th of the tank is 5 hours. What is the time taken to fill up the tank?

  5. Q 115

    The number  of days in which A and B together can finish a piece of work is 12 days less than the time taken by A alone and 27 days less than the time taken by B alone to finish the work. If A and B completed the work in 15 days with the help of C and got a total compensation of Rs 3000 for the work, then what is the share of C?

  6. Q 116

    6 men and 8 women together can complete a piece of work in 10 days. Work done by a woman in one day is equal to half the work done by a man in one day. If 10 women are working alone, in how many days will the work get completed?

  7. Q 117

    Amit and Babu can do a piece of work in 18 days; Babu and Chandu can do it in 24 days Amit and Chandu can do it in 36 days. In how many days will Chandu finish it alone?

  8. Q 118

    45 men can complete a work in 16 days. Six days after they started working, 30 more men joined them. In how many days the total work will be completed ?

  9. Q 119

    Atul takes 8 hours to do a job.  Bhumi takes 10 hours to do the same job. How long should it take both Atul and Bhumi, working together but independently, to do the same job?

    Show answerHide answer

    Answer: Option B. <span class="math-tex">4494\frac{4}{9}</span>

    Open question
  10. Q 120

    Mayur can complete a work in 12 days. Varun alone can complete it in 12 days. If Mayur does the work only for half a day daily, then in how many days Varun and Mayur together will complete the work?