Sachin does half as much work as Shashi in three fourths of the time. If together they take 18 days to complet…

Q 128

Sachin does half as much work as Shashi in three fourths of the time. If together they take 18 days to complete the work, how much time will Shashi take to do it?

Show answerHide answer

Answer: Option B. 30 days