A can do a piece of work in 12 days while B alone can do it in 15 days. With the help of C they can finish it…

Q 127

A can do a piece of work in 12 days while B alone can do it in 15 days. With the help of C they can finish it in 5 days. If they are paid Rs. 960 for the whole work how much money A gets?

Show answerHide answer

Answer: Option D. Rs. 400