Q 134
A company contracts to paint 3 houses. Mr. Brown can paint a house in 6 days while Mr. Black would take 8 days and Mr. Blue 12 days. After 8 days Mr. Brown goes on vacation and Mr. Black begins to work and he leaves after working of 6 days. How many days will it take Mr. Blue to complete the contract?