Q 15Ram can complete ¼ th part of work in 8 days and Shyam can complete 2/4 th of the work in 6 days and Naresh can complete ¾th the work in 12 days. In how many days can they together complete it?AOption A: 611176 {11 \over 17 }BOption B: 511175 {11 \over 17 }COption C: 811178 {11 \over 17 }DOption D: 711177 {11 \over 17 }