Q: A certain work can be completed in 100 days by a certain number of men. But, due to the absence of 10 peopl…

Q 22

A certain work can be completed in 100 days by a certain number of men. But, due to the absence of 10 people it could be completed in 110 days. How many workers were employed initially ?

Show answerHide answer

Answer: Option B. 110