A, B and C can complete a work in 10, 15 and 20 days respectively. A and B start it together. B is replaced by…

Q 27

A, B and C can complete a work in 10, 15 and 20 days respectively. A and B start it together. B is replaced by C after 2 days. A leave it after one more day. In how many days work was completed?

Show answerHide answer

Answer: Option B. 1311313 {1 \over 13 }