Q 67Amar can complete ¼ work in 3 days and Bhaskar can complete 1/6 th of the work in 4 days. If they work on it together, they get Rs 1800. Find the amount received by Amar.AOption A: Rs 600BOption B: Rs 1000COption C: Rs 1080DOption D: Rs 1200