Time and Work questions and answers, page 7

Questions 61 to 70 of 286

  1. Q 61

    12 men can complete one-third of the work in 8 days. In how many days can 16 men complete that work?

  2. Q 62

    12 men complete a work in 18 days. Six days after they had started working, 4 men joined them. How many days will all of them take to complete the remaining work?

  3. Q 63

    A, B and C can complete a piece of work in 24, 6 and 12 days respectively. Working together, they will complete the same work in

    Show answerHide answer

    Answer: Option C. 337days3{3\over 7}days

    Open question
  4. Q 64

    A can do a piece of work in 4 hours; B and C can do it in 3 hours. A and C can do it in 2 hours. How long will B alone take to do it ?

  5. Q 65

    A and B together can complete a work in 10 days. A alone can do it in 40 days. In how many days B alone can complete it?

    Show answerHide answer

    Answer: Option A. 403{40\over3}

    Open question
  6. Q 66

    P takes 5 more hours to complete a work in comparison to Q. They work together for 6 hours. In how many days can Q complete the same work.

  7. Q 67

    Amar can complete ¼ work in 3 days and Bhaskar can complete 1/6 th of the work in 4 days. If they work on it together, they get Rs 1800. Find the amount received by Amar.

  8. Q 68

    30 Men can complete a work in 25 days. In how many days can 75 men complete it?

  9. Q 69

    Ratio between the time taken by A and B to complete a certain work is 4 : 5. If together they can complete a work in 20 days, in how many days can A alone complete it?

  10. Q 70

    A, B and C can complete a piece of work in 10, 12, and 15 days respectively, They started the work together. But A left the work before 5 days of its completion. B also left the work 2 days after A left. In how many days was the work completed?