Q 61
12 men can complete one-third of the work in 8 days. In how many days can 16 men complete that work?
12 men can complete one-third of the work in 8 days. In how many days can 16 men complete that work?
12 men complete a work in 18 days. Six days after they had started working, 4 men joined them. How many days will all of them take to complete the remaining work?
Ratio between the time taken by A and B to complete a certain work is 4 : 5. If together they can complete a work in 20 days, in how many days can A alone complete it?
A, B and C can complete a piece of work in 10, 12, and 15 days respectively, They started the work together. But A left the work before 5 days of its completion. B also left the work 2 days after A left. In how many days was the work completed?