Q 138A can do a piece of work in 20 days and B in 30 days. They work together for 7 days then both leave the work. Then C alone finishes the remaining work in 10 days. In how many days will C finish the full work?AOption A: 25 daysBOption B: 30 daysCOption C: 24 daysDOption D: 20 daysEOption E: None of these