S and U started working on alternate days. S worked with 150% of her efficiency and U worked at (6/5)th of her…

Q 289

S and U started working on alternate days. S worked with 150% of her efficiency and U worked at (6/5)th of her daily efficiency. If S starts initially, then how many days require by them to complete the work?

Show answerHide answer

Answer: Option C. 20 days