Q 263A can finish a work in 10 days. B can finish the same work in 12 days. The days required to finish the work by both of them together areAOption A: 1<span class="math-tex">1 11{1 \ \over 11}</span>BOption B: 2<span class="math-tex">5 11{5\ \over 11}</span>COption C: 5<span class="math-tex">5 11{5\ \over 11}</span>DOption D: 4<span class="math-tex">3 11{3\ \over 11}</span>