A can do a piece of work in 20 days and B in 30 days. They work together for 7 days and then both leave the wo…

Q 51

A can do a piece of work in 20 days and B in 30 days. They work together for 7 days and then both leave the work.  Then C alone finishes the remaining work in 10 days. In how many days will C finish the full work?

Show answerHide answer

Answer: Option C. 24 days