A builder decided to build a farm house in 40 days. He employed 100 workers in the beginning and 100 more afte…

Q 247

A builder decided to build a farm house in 40 days. He employed 100 workers in the beginning and 100 more after 35 days and completed the construction in stipulated time. If he had not employed the additional workers, how many days behind schedule would it have been finished?

Show answerHide answer

Answer: Option D. 5