Time and Work questions and answers, page 26

Questions 251 to 260 of 286

  1. Q 251

    A can do a piece of work in 8 days and B can do it in 10 days separately. How many days would it take for both A and B to finish the same work together?

  2. Q 252

    Three brothers Ramesh, Aman and Shishir running a family business of making clay pot. Ramesh can make 60 pot in 15 days, while Aman alone can do it in 10 days. They all work together for 5 days and the rest of the work is done by Shishir in 3 days. If they earn Rs. 8100 by selling all pot, how should they divide the money?

    Show answerHide answer

    Answer: Option E. Rs. 2700, Rs. 4050, Rs. 1350

    Open question
  3. Q 253

    A can do 1/3rd of a work in 5 days and B can do 2/5th of this work in 10 days. Both A and B, together can do the work in

    Show answerHide answer

    Answer: Option C. 9 <sup>3</sup>/<sub>8</sub> days

    Open question
  4. Q 254

    A group of people is assigned a task of checking papers. They are supposed to continue working without rest, and checking 1 paper is considered as 1 piece of work. 2 men and 4 women together can do 125% of this piece of work in an hour. A man works twice as fast as a woman does. How much of the same work can 4 men and 2 women finish in an hour?

    Show answerHide answer

    Answer: Option D. 156.25% of a piece of work

    Open question
  5. Q 255

    If all 4 pipes are opened together, how much hour would it take to fill the tank? Assume D can empty the tank twice as fast as C.

  6. Q 256

    If pipes A, B and C together can fill the tank in 9 hours then, calculate the part of tank filled by A and B together in an hour.

  7. Q 257

    How long would it take if 30 boys and 38 men were employed and how much would it cost?

    Show answerHide answer

    Answer: Option C. 39 days and Rs. 15834

    Open question
  8. Q 258

    If 18 women are included in the task then find the cost if 2 women can do as much work as 1 man and wages of 6 women is equal to wages of 5 men.

    Show answerHide answer

    Answer: Option A. Rs. 18048.33

    Open question
  9. Q 259

    If 7 spiders make 7 webs in 7 days, then 1 spider will make 1 web in how many days?

  10. Q 260

    10 women can do a piece of work in 6 days, 6 men can do same work in 5 days and 8 children can do it in 10 days. What is the ratio of the efficiency of a woman, a man and a child respectively?