## Q201

50 men can construct a road in 60 days. They started the work together. But at the end of every 15th day, 10 men left the work. What part of work was left incomplete at the end of allotted time?

A. 1/4
B. 3/10
C. 7/10
D. 17/20

Answer: B. 3/10

Page: https://www.megaexam.in/question/50-men-can-construct-a-road-in-60-days-they-started-the-work-together-but-at-the-end-of-every-15-lt-sup-gt-th-lt-sup-gt-day-10-men-left-the-work-what-part-of-work-was-left-incomplete-at-the-end-of-allotted-time-688469628651753479

## Q202

A tank has a leak which would empty the completely filled tank in 15 hours. If the tank is empty and a tap is opened which admits 5 litres of water per minute in the tank, it takes 10 hours to fill the tank. What is the capacity of the tank (in litres)?

A. 2400
B. 1800
C. 9000
D. 7200

Answer: B. 1800

Page: https://www.megaexam.in/question/a-tank-has-a-leak-which-would-empty-the-completely-filled-tank-in-15-hours-if-the-tank-is-empty-and-a-tap-is-opened-which-admits-5-litres-of-water-per-minute-in-the-tank-it-takes-10-hours-to-fill-the-tank-what-is-the-capacity-of-the-tank-in-litres-688469628702085121

## Q203

A can do a piece of work in 12 days and B in 16 days. A began the work alone, After some days B joined the work. The work was completed in 9 days, in all. How many days before the completion of the work did B join the work?

A. 12
B. 10
C. 4
D. 9

Answer: C. 4

Page: https://www.megaexam.in/question/a-can-do-a-piece-of-work-in-12-days-and-b-in-16-days-a-began-the-work-alone-after-some-days-b-joined-the-work-the-work-was-completed-in-9-days-in-all-how-many-days-before-the-completion-of-the-work-did-b-join-the-work-688469628756611074

## Q204

Aditya alone can finish the work in 12 days and Raman can alone finish the work in 18 days. If they work together and they are daily paid Rs. 550. What is the amount that Aditya will receive out of it?

A. Rs. 110
B. Rs. 150
C. Rs. 175
D. Rs. 220
E. Rs. 330

Answer: E. Rs. 330

Page: https://www.megaexam.in/question/aditya-alone-can-finish-the-work-in-12-days-and-raman-can-alone-finish-the-work-in-18-days-if-they-work-together-and-they-are-daily-paid-rs-550-what-is-the-amount-that-aditya-will-receive-out-of-it-688469628911800321

## Q205

Max’s efficiency is 2/5th Kendrick’s efficiency. Max starts off three pieces of work and works for a day alone and Kendrick joins him for the next half a day. As Max leaves after that, Kendrick bucks up and doubles his efficiency. If he can finish the remaining work alone in 4 hours, then in how much time could Max and Kendrick together do one piece of work at initial efficiency?

A. <span class="math-tex">$3\frac{1}{{25}}$</span>&nbsp;days
B. 1 day
C. <span class="math-tex">$1\frac{5}{{12}}$</span>&nbsp;hours
D. 126/43<sup>rd</sup> of a day
E. None of these

Answer: E. None of these

Page: https://www.megaexam.in/question/max-amp-rsquo-s-efficiency-is-2-5-lt-sup-gt-th-lt-sup-gt-kendrick-amp-rsquo-s-efficiency-max-starts-off-three-pieces-of-work-and-works-for-a-day-alone-and-kendrick-joins-him-for-the-next-half-a-day-as-max-leaves-after-that-kendrick-bucks-up-and-doubles-his-efficiency-if-he-can-finish-the-remaining-work-alone-in-4-hours-then-in-how-much-time-could-max-and-kendrick-together-do-one-piece-of-work-at-initial-efficiency-688469629066989569

## Q206

Two workers A and B are engaged to do a work. A working alone takes 8 hours more to complete the job than if both worked together. If B worked alone, he would need $4\frac{1}{2}$  hours more to complete the job than they both working together. What time would they take to do the work together?

A. 4 hours
B. 5 hours
C. 6 hours
D. 7 hours
E. None of these

Answer: C. 6 hours

Page: https://www.megaexam.in/question/two-workers-a-and-b-are-engaged-to-do-a-work-a-working-alone-takes-8-hours-more-to-complete-the-job-than-if-both-worked-together-if-b-worked-alone-he-would-need-lt-span-class-quot-math-tex-quot-gt-4-frac-1-2-lt-span-gt-amp-nbsp-hours-more-to-complete-the-job-than-they-both-working-together-what-time-would-they-take-to-do-the-work-together-688469629306064897

## Q207

The quantity of water which flows through a pipe is proportional to the square of its diameter. If a pipe of 5 cm diameter can fill a tank in 1min. How long would 3 pipes of 3cm, 4cm and 5cm diameter together take to fill it?

A. 2 min.
B. 1.5 min.
C. 1 min.
D. 30 sec
E. None of these

Answer: D. 30 sec

Page: https://www.megaexam.in/question/the-quantity-of-water-which-flows-through-a-pipe-is-proportional-to-the-square-of-its-diameter-if-a-pipe-of-5-cm-diameter-can-fill-a-tank-in-1min-how-long-would-3-pipes-of-3cm-4cm-and-5cm-diameter-together-take-to-fill-it-688469630119759873

## Q208

A machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines are started at 9 a.m. while machine P is closed at 11 a.m. and the remaining two machines complete the work. Approximately at what time will the work be finished?

A. <p>11:30 a.m.</p>
B. 12 noon
C. 12:30 p.m.
D. 1 p.m.
E. 2 p.m.

Answer: D. 1 p.m.

Page: https://www.megaexam.in/question/-lt-p-gt-a-machine-p-can-print-one-lakh-books-in-8-hours-machine-q-can-print-the-same-number-of-books-in-10-hours-while-machine-r-can-print-them-in-12-hours-all-the-machines-are-started-at-9-a-m-while-machine-p-is-closed-at-11-a-m-and-the-remaining-two-machines-complete-the-work-approximately-at-what-time-will-the-work-be-finished-lt-p-gt-688469630144925697

## Q209

Two pipes A, B can fill a cistern in 10 hours and 12 hours respectively working alone while the leak present can empty the cistern in 15 hours. If both pipes and the leak are opened together, then find the time taken to fill the cistern.

A. 7 hours
B. <span class="math-tex">$8\frac{4}{7}$</span>&nbsp;hours
C. <span class="math-tex">$7\frac{6}{7}$</span>&nbsp;hours
D. <span class="math-tex">$9\frac{5}{6}$</span>&nbsp;hours

Answer: B. <span class="math-tex">$8\frac{4}{7}$</span>&nbsp;hours

Page: https://www.megaexam.in/question/two-pipes-a-b-can-fill-a-cistern-in-10-hours-and-12-hours-respectively-working-alone-while-the-leak-present-can-empty-the-cistern-in-15-hours-if-both-pipes-and-the-leak-are-opened-together-then-find-the-time-taken-to-fill-the-cistern-688469630174285829

## Q210

If two pipes P and Q are such that, they can fill a large tub in 6 and 18 minutes respectively. They are opened on alternate minutes. Find in how many minutes, the tub shall be full?

A. 6 min.
B. 10 min.
C. 18 min.
D. 24 min.
E. None of the above

Answer: E. None of the above

Page: https://www.megaexam.in/question/if-two-pipes-p-and-q-are-such-that-they-can-fill-a-large-tub-in-6-and-18-minutes-respectively-they-are-opened-on-alternate-minutes-find-in-how-many-minutes-the-tub-shall-be-full-688469631499685889

Next page: https://www.megaexam.in/aptitude/time-and-work.md?page=22